Work to
begin on second runway
All things
being equal, the Nnamdi Azikiwe International Airport’s (NAIA) new terminal in
Abuja will open for operations February next year.
The
terminal, built at the estimated cost of N61.2 billion ($200 million) is a
partnership between the Nigerian government and the China Civil Engineering
Construction Corporation (CCECC).
The new
terminal, according to state officials, is to offer befitting service to
airport users that are visiting the Federal Capital and accommodate new traffic
on account of the second runway already penciled for 2018.
The National
Assembly joint committee on aviation, on an oversight function Tuesday, was
impressed with the level of work at the facility, concluding that it is 80 per
cent ready.
While the
construction company, CCECC, said the terminal will be ready February barring
shortage in power and water supply, the committee urged the handlers to ensure
all necessary equipment are in place before the facility officially open for
use.
It will be
recalled that the new terminal is one of the four terminals for construction in
the N153 billion ($500 million) loan deal between the Federal Government and
CCECC in July 2014. However, delay in the payment of counterpart funding by
Nigeria has stalled progress of the work with delay in completion date.
Chairman,
Senate Committee on Aviation and leader of the team, Adamu Aliero, said the
joint committee is working with the Ministry of Aviation on ways to secure
funds to ensure the terminal is delivered with all equipment in place.
On the CCECC
Project Manager’s concern over power and water supply shortage, Aliero assured
that the ministry of aviation is already aware of the challenge and working to
resolve it.
“And once
they bring it to the notice of the legislature, we will do the needful and give
necessary support because we need this terminal to be put to use immediately
after completion.
“There is no
point having a terminal without water and electricity. The existing power and
water supply is not adequate to accommodate the terminal without an upgrade.”
“The
terminal would be completed and commissioned before the end of next year. It is
already 80 per cent ready. What is left to be done is just the finishing and
the equipment are already on ground. The project manager said the control tower
and fire station need to be relocated. If the fire station and control tower
are relocated, maybe we would commission the facility earlier than the end of
next year,” Aliero said.
The chairman
added that there is no going back on the construction of a second runway for
the Abuja Airport “because of the increasing passenger traffic and capacity for
the airport.”
He said the
Abuja aerodrome is the only major airport in Nigeria without a second runway,
adding that the National Assembly had already made provision for the runway in
the 2018 Appropriation Bill.
He said all
that is left is for the ministry of aviation to make arrangement for the
procurement and award for the contract.
“Lagos,
Kaduna, Kano and Port Harcourt all have second runway. Abuja being the federal
capital territory deserves a second runway with the attendant passenger inflow
and number of flights coming into the airport.
“We do not
need a situation where we have to wait or divert to Kaduna International
Airport again with the horrendous experience before building a second runway.
“This is why
the National Assembly has approved the construction of second runway for Abuja
and luckily the ministry is working to ensure that the procurement and award of
contract is done before the end of this year and if it is awarded there would
be enough funding for next year.”
Earlier,
Project Manager, Kelvin Lee, said unless there is an upgrade of existing power
and water supply, the completion date will be delayed.
Lee said it
would be of no value to complete a terminal of such magnitude without adequate
power and water supply.
He urged
government to facilitate funding to accelerate the provision of support
equipment that would enable the company deliver the terminal before the end of
next year.
Lee said the
company was working within its scope to complete the terminal, but will require
government to relocate the control tower and fire station that currently pose
an obstacle to some sections of the new terminal.
Part of the
sections of Abuja Airport visited by the committee include Wing D , section of
the terminal, the resurfaced runway, the new Chinese International terminal,
the flight decoding laboratory of the Accident Investigation Bureau (AIB) and
proposed headquarters of the Nigerian Civil Aviation Authority ( NCAA).
0 Comments