The Federal
Government has signed Power Purchase Agreement (PPA) with Mabon Nigeria
Limited, which is currently executing 40 megawatts hydro-power project.
The
government, represented by the Managing Director of the Nigeria Bulk
Electricity Trading Plc (NBET), Dr. Marilyn Amobi, said the agreement would
enable the government buy electricity from the investor and sell to the
distribution companies (DisCos).
Amobi said
though the government is not making initial payment now, such payment would be
made based on metered capacity when the investor starts selling electricity on
completion of the project.
She said:
“We have been on this for a couple of months. It is a hydro-power project based
in Dadinkowa, Gombe State and they have electricity they want to inject into
the grid.
“What we are
signing is just a binding document for us to engage with them and buy their
electricity which we will then sell to the distribution companies and other
general service companies which buy electricity from NBET. There is no initial
payment until when they start selling based on their metered energy.”
However, the
Project Development Consultant, Christopher Cyril, who represented Mabon
Limited, noted that though the signing of the PPA had taken long before being
realised, but with the signing now, the investor has been assured of return on
the investments.
Cyril, who
stated that so far, $48 million had been invested on the project, which is at
about 80 per cent completion while the total cost of the project is $68
million, said: “So, we are going to put all eagerness until the last paper is
signed and once we have it, I think it is going to reassure us as a company as
soon as we are up and running, that we will make a viable business and recovery
of investment cost is also guaranteed.
“The project
concession was awarded in 2005, and like in the industry, once a concession is
given, the next thing is the PPA to enable the developer mobilise funds,
mobilise to site but it so happened that after the concession was given, as
result of change in government and policies, all these things contributed to
the delay in the PPA which we finally got today.
“However,
while waiting for the PPA to come, Mabon as a company decided to mobilise with
our personal funds to site. If you come to the site, the project is at about 80
per cent completion stage.”
“Without
looking at my books, we have invested nothing less than $48 million because
when we inherited the dam, it was like an abandoned place. So, the first thing
we had to do is what is called stability test and we try to stabilise the dam,
procure all the hydro mechanical equipment and carry out other civil works in
the dam which was even outside the concession.
“The total
cost of completing the project is about $68 million and it is 40mw installed
capacity with twin-turbine and if we are able to close the deal by December,
seven to eight months after, the first unit will be commissioned while others
will follow subsequently,” he further said.